|
|
My Sample Resume Education
Project Management
Summary
Over 3.5 years (45 Months) experience in Project Management. Over 5000 Hours in managing
various development and implementation projects in the software industry.
1) Duration: May 1998 – Present (24 Months), 3700 Hours
As a Project Manager at ABC Inc.., managed the roll out of software products
and implementation
projects for various clients.
The following projects were executed during the above time frame: i)
Software Development Projects – a)
Rollout of Automated Import System b)
Rollout of Automated Protest System ii)
Implementation Projects – a)
Customization and Implementation of Automated Protest System for 2
Clients b)
Customization and Implementation of Automated Imports System iii)
Other Projects – a)
Year 2000 Readiness Project for ISSI
2)
Duration:
June 1997 – March 1998 (10 Months), 1200 Hours At 123 Inc.., managed a project team of 8 Software Engineers and 2 Quality Analysts. The Project team was responsible for
i)
Development of CSM-Maveric, an
inventory control software for the oil industry
3)
Duration:
October 1996 – May 1997 (8 Months), 700 Hours
i)
Managed a project to set-up the
software development division for DSC GMBH for MANN
Project 1 Automated Protest System May
1998 - September 1998
Total
Time Spent: 740 Hours
Initiating
Process, Time Spent: 20 Hours
·
Had discussions to determine the
need for the development of the Automated Protest System and to understand the
expectations of the executive management ·
Based on the inputs received from
the management and the discussions with the functional experts the Project
Charter was developed ·
Was named the Project Manager for
the development of Automated protest System ·
Was involved in the project team
finalization ·
Conducted team meeting during which
the team members were introduced Planning
Process, Time Spent: 260 Hours
·
Scope Planning Was
involved in the development of a scope statement which consisted of the
following details: -
Major deliverables of the project,
viz. 1)
Protest Entry Module 2)
Customs Transmission Module 3)
User Manual 4)
Installation Guide -
Broad function of each of the above
module -
Analysis and justification of the
technology to be adopted -
The Coding standards to be adopted ·
Scope Definition The
following activities were carried as part of the scope definition. The two
modules of the software which were defined as deliverables in scope statement
was further sub-divided specific deliverables to each module: -
Worked with the functional group to
document the functionality of the above modules. Based on the inputs received
from the functional group the functional specification document was developed -
Co-ordinated discussions between
the functional and the development group -
The functional requirements
outlined in the functional specification document was translated to the
technical Design Document, which formed the basis of coding -
Had discussions with the
development and testing teams to develop the formats of the following, to be
used during the testing phase: ·
Unit
Test Plan ·
Integration
Test Plan -
Developed the WBS for the project
outlining the various activities ·
Activity Definition - Using the WBS the various activities of the project were clearly identified and defined ·
Activity Sequencing - The relationship between the various activities were determined and the activity sequence was developed ·
Activity Duration Estimation and
Schedule Development -
The time required for each activity
was estimated and the project schedule was developed ·
Resource Planning -
Not Applicable ·
Cost Estimating -
Not Applicable ·
Cost Budgeting -
Not Applicable ·
Quality Planning -
Conducted discussions on the
various testing procedures to be adopted during the development and the same
were documented ·
Organizational Planning & Staff
Acquisition -
Not applicable ·
Communication Planning -
The communication methodology to be
followed during the entire course of the project was discussed and determined.
Standard templates for various reports were developed ·
Risk Identification, Quantification
and Response Development -
The various external risks (Customs
regulations) and internal risks (technology migration) involved in the product
development were identified, quantified and the probable responses should the
risks arise were formulated ·
Procurement Planning -
Not Applicable ·
Solicitation Planning -
Not Applicable ·
Project Plan Development -
The project plan was developed
outlining the various activities, resources who will be responsible for the
activities, the time frame when each activity will begin and end, various
methods of communication internal and external to the project etc. Executing
Process, Time Spent: 380 hours
·
Project Plan Execution -
Ensured that the various tasks
identified in the project plan were completed. The progress of each task was
monitored. The quality of performance of each task was tracked. The changes of
scope, which occurred during the project plan execution were documented and the
schedule was revised based on the change and the project was executed. ·
Information Distribution -
Monitored the project progress
using the various reporting formats. The management was informed of the
progress. The testers were informed of the daily progress and the new features
to be tested. The testing feedback was distributed back to the development team
for the corrections ·
Team Development -
Conducted regular meetings were to
ensure interactions between the team members. One team member was asked to test
the other persons work and vice versa to induce the sense f team spirit in the
team which lead to team development ·
Quality Assurance -
Monitored the testing of the system
features based on the test plans developed to ensure the proper performance and
quality of the developed software ·
Scope verification -
Each feature of the developed
software was compared against the scope definition to ensure that the deviation
from the scope definition was minimum. Conducted review meetings at the
completion of each feature to verify if it adhered to the scope definition ·
Solicitation -
Not Applicable ·
Source Selection -
Not Applicable ·
Contract Administration -
Not Applicable Controlling
Process, Time Spent: 60 Hours ·
Performance Reporting -
The progress of the development was
monitored continuously through various reports and status review meetings.
Informed the management on the progress of the project through presentations and
demonstrations. ·
Overall Change Control -
The Changes in the scope and
schedule of the project was constantly monitored using change control documents
and project plan revisions ·
Quality Control -
Held meetings with the testing team
to ensure quality control of the product ·
Risk Response Control -
Not applicable Closing
Process, Time Spent: 20 Hours ·
Administrative Closure -
Project completion meeting was
completed with the project team and the product was signed off for release. The
implementation team was trained on the product and the protest system was handed
over to the implementation team. Complete documentation related to the system
was handed over. The project team was relieved of the responsibilities of the
product and the project was formally closed ·
Contract
Close-out -
Not
applicable Project 2 |