Project is proposed to be implemented as under:-
� | Commencement | Completion |
i) Acquisition of land | Already Acquired | |
ii) Infrastructural Development | Oct. 2001 | Mar. 2002 |
iii) Civil work | � | |
a. Factory building | Nov. 2001 | April 2002 |
b. Machinery foundation | Dec. 2001 | April 2002 |
c. Auxiliary building | Apr. 2001 | Aug. 2001 |
d. Administrative Building | � | |
e. Misc. building | � | |
iv) Indigenous Machinery | � | |
a. Placement of orders | Nov. 2001 | Nov. 2001 |
b. Delivery on site | Jan. 2002 | Feb. 2002 |
v) Arrangement for power & Water | Dec. 2001 | Jan.2002 |
vi) Erection of Facilities | Feb. 2002 | Feb. 2002 |
viii) Commissioning | May 2002 | June 2002 |