Street Activity Permit Process |
Applications available at the office
of Community Board 4.
All applications must be submitted at least
nine (9) weeks in advance. (Not including weekends)
Applications must include petition from block.
Apply early - only 10 street closings allowed on any given day.
A $15.00 money order Payable to NYC Department of Finance must
accompany the completed application.
No Street Closing Permits: Block Parties, Clean-ups, Religious
Ceremonies, etc. . |
- Puerto Rican Day Parade Weekend - Friday, Saturday, Sunday - June 12-14, 2009
- Dominican Day Parade Weekend - Friday, Saturday, Sunday - August 7-9, 2009
- Independence Day - Saturday, July 4, 2009
No Parade, Street
Permits, Sound Permits will be issued ordered by the New York City
Police Department.
*
The 83rd Pct. has produced a street closing DENIAL LIST. Please call
the Community Board Office at
718-628-8400 for your block status.*
** Applications will only be accepted at the Community Board office
Monday � Friday from 10am � 4pm.**
If you have any questions, please call the Community Board Office at
718-628-8400.
As result of a recent decision by the
United States court of appeals, second circuit, section 10-108 of NYC
administrative code for sound device: block parties shall end no later
than 9pm. This is in conjunction with local law 13 requiring amplified
sound device permits to end no later than 8 pm or sundown, whichever
comes earlier, if within 50 feet of a residential building. Sound
permits may be obtained at the local precinct (83rd Precinct - 480
Knickerbocker Avenue, corner of Bleecker Street) no later than 5 days
before the event. The fee has been reinstated to $45.00 per block
party, should you plan to have amplified sound.
All applications for multi-block and/or multi-day street events shall
be obtained at the office of the Community Board or the Street
Activity Permit Office (SAPO) and shall be filed directly with SAPO no
later than December 31st, unless local Community Board request an
earlier filing date. In such cases, filing at SAPO by such earlier
date is required. Community Boards must return applications with their
comments no later than March 1st. Please be advised that
rain dates or other forms of make up dates will no longer be accepted
for multi-day and/or multi-block events.
|
|
|